Description
Submission of 5% Performance Guarantee (Rs. 83,34,850.00) within 15 days of LOI (due 3 June 2025). Failure may result in EMD forfeiture.
LOI 19 May 2025 → target completion 19 Aug 2026 (457 days contractual period).
| Milestone | Target date | Status |
|---|---|---|
| LOI Date | May 19, 2025 | Completed |
| Agreement preparation fee | May 26, 2025 | Completed |
| Reckoned date of commencement | May 29, 2025 | Completed |
| Project planning submission | May 29, 2025 | Completed |
| Performance Guarantee | Jun 3, 2025 | Completed |
| Project completion date | Aug 19, 2026 | Upcoming |