Construction of CHC (G+2) building at Paikmal in Paikmal Block of Bargarh, Odisha.
LOI date: 19 May 2025. Contractual completion: 19 August 2026 (15 months from LOI).
Key contractual milestones are listed as separate status entries (CHC · …). Past milestones are recorded as completed per project records.
Penalties under the LOI may include EMD forfeiture for failure to meet deadlines (e.g. Performance Guarantee within 15 days of LOI).
LOI date: 19 May 2025. Contractual completion: 19 August 2026 (15 months from LOI).
Key contractual milestones are listed as separate status entries (CHC · …). Past milestones are recorded as completed per project records.
Penalties under the LOI may include EMD forfeiture for failure to meet deadlines (e.g. Performance Guarantee within 15 days of LOI).